INDOT FLOYD COUNTY, IN-Paving will continue along westbound Interstate 64’s center lane this week through Wednesday night (SEPTEMBER 21) between the hours of 7 p.m. and 8 a.m. Milling and resurfacing operations in the center lane also require overnight closures of the westbound right lane.
The westbound right lane and I-64 ramps remain to be milled and paved. That work will begin—weather permitting—at the end of the week. INDOT’s contract completion date is October 31.
Paving operations require westbound I-64 ramp closures beginning at 9 P.M. at these locations:
TUESDAY—Westbound Exit 119, to U.S. Highway 150
WEDNESDAY—Westbound Exit 118, S.R. 62/SR 64
Again, Westbound off ramps as scheduled to reopen by 8 A.M. You can see the locations here: